A Booster common dome section was flipped, work on Booster 4 and Ship 20 continued, and an aft flap alignment jig was spotted attached to Ship 21 ahead of flap installation.
Video and Pictures from Mary (@BocaChicaGal) and Nic (@NicAnsuini). Edited by Jack (@theJackBeyer).
All content copyright to NSF. Not to be used elsewhere without explicit permission from NSF.
Click "Join" for access to early fast turnaround clips, exclusive discord access with the NSF team, etc - to support the channel.
Rolling Updates and Discussion: https://forum.nasaspaceflight.com/index.php?board=72.0
Articles: https://www.nasaspaceflight.com/?s=Starship
NSF Store: https://www.nasaspaceflight.com/shop/
L2 Boca Chica (more clips and photos) from BC's very early days to today.
https://forum.nasaspaceflight.com/index.php?topic=47107.0
(Join L2 and support NSF here: https://www.nasaspaceflight.com/l2/)
0:00 - Sunrise
0:18 - The Launch Site
0:35 - Crews Work on Ship 20
3:47 - Orbital Tank Farm Construction
4:39 - Orbital Launch Mount Construction
5:12 - Orbital Launch Mount and Chopsticks
5:28 - Quick Disconnect Arm
5:45 - Crews Work on Booster 4
7:28 - Aft Flap Alignment Jig on Ship 21
8:10 - Ship 21 (left), and Ship 22 (right) in the Mid Bay
8:33 - Wide Bay Construction
9:06 - Barrel Sections at the Production Site
9:46 - Booster Quick Disconnect Hood
10:03 - Ship 21 Nosecone Construction
10:49 - Booster 5 in the High Bay
11:16 - Flip Rig Attached to Crane
11:59 - Booster Common Dome Section Flipped